MassPort Reports that Runway Closures Will End on June 23

This week, almost a month into work, the Massachusetts Port Authority (Massport) is pleased to report that the critical Runway 4R-22L Resurfacing and Approach Light Pier Replacement Safety Project is progressing on schedule and will result in the rehabilitation of one of Logan Airport’s key runways and the replacement of a light pier used in operations.

The runway is expected to reopen for use by June 23.

This project is necessary to maintain the high standards of safety at Logan, MassPort said.

The runway reconstruction project began in mid-May with the closure of Runway 4R-22L and is expected to continue through June 23 as critical work is done to maintain and repair one of Logan’s major runways. The paving in the majority of the phases has been completed, with pavement markings, landscaping and lighting work remaining.

Additional work not requiring the extended closure of 4R-22L will continue through November.

The continuous work schedule and closure was agreed upon in consultation and coordination with the airlines and the Federal Aviation Administration enhances safety and will reduce the overall construction timeline, bringing normal operations back faster. This important project is running on schedule and Massport expects Runway 4R-22L to be open again for use at the end of the day on June 23.

“Safety is Massport’s top priority,” said Massport CEO Thomas P. Glynn. “While routine, this project will repair one of our critical runways ensuring the safest environment for the traveling public, our employees and communities. We appreciate the patience of our neighboring communities and the traveling public as flight patterns have changed and apologize for any inconvenience this work may have caused.”

This work is part of routine, but essential, safety maintenance projects that occur annually throughout airport property. The main goal of this project will be to replace the asphalt pavement that has deteriorated. The pavements were last rehabilitated in the years 2005, 2006 and 2008.

This project will include work both on the runway and at the runway’s end to replace the light pier. The existing wooden pier will be replaced with a concrete pier designed to last 75 years; the current pier was originally constructed in 1955, with repairs last made in 2016. Work on the approach light pier replacement is progressing according to schedule.

Massport Community Relations can be reached at 617-568-3711.

Leave a Reply

Your email address will not be published. Required fields are marked *