The City will begin design of a major rehabilitation of Beacham Street in the New England Produce Center area from Spruce Street to the Everett line, said City Planner Alex Train.

That comes due to the fact that the City was just recently awarded an unexpected $3 million grant for the project from the federal Department of Commerce’s Economic Development Administration.

Train said the City has proposed a $5 million capital investment in the project for the Fiscal Year 2020 Capital Improvement Plan (CIP), giving them $8 million total to complete the project.

He said they will begin as soon as they can.

“We are excited to get this started,” said Train. “We are scheduled to start design and engineering on July 1. We will hopefully break ground on construction July 1, 2019. I expect there would be a three-year construction timeline. During that time and before, we will be coordinating with abutters, residents and businesses.”

The plan includes completely repurposing the roadway from a predominantly industrial truck route to a major automobile/pedestrian/cyclist east-west corridor throughway.

That will mean it will get a new surface, a new roadway, a new sidewalk on one side, a shared-use path on the southerly side with a buffered bike/pedestrian path, stormwater/drainage improvements, new lighting, new street trees, new signals at the intersection of Spruce and Williams Streets.

In addition, Train said they are working with the City of Everett to coordinate the design so that the Everett project matches the Chelsea project.

“They will be mimicking our design so there will be a contiguous and similar cyclable and walkable roadway from Chelsea to Everett,” he said.